Current Impacts

Jan. 23, 2020: Progress Update

January construction efforts are continuing at both roundabouts: 

  • Crews are continuing lighting installation and drainage work at the Jeremy Ranch Park-n-Ride Lot. 
  • Installation efforts of the WB I-80 on-ramp wild life guard will occur over the next two weeks. The on-ramp will be constricted to an 11’ lane. 
  • Crews continue concrete work and retaining walls on the tunnel under EB 1-80 on-ramp. 
  • Rock wall installation will occur at Kilby Rd (near Cedar Drive) over the next several weeks. 
  • Sign bases are poured and ready for the large roundabout directional signs (containing street names). Placement is anticipated by the end of January. 
  • Pinebrook roundabout lighting anticipated by end of week.

Progress email updates will be sent biweekly until the spring. 

ICYMI: the temporary pedestrian path is now open!


Also last week crews poured a stamped concrete “landscape feature” on the southside of the Jeremy Store. This is a special exit point for fuel and other delivery trucks only and is not intended for the general public to utilize. Posts and chains will be installed at a later date.

To download a printable map of the current configuration click here. 

Drivers should:

  • Follow all detour signage
  • Expect travel delays
  • Use caution

*Construction schedules are weather dependent and subject to change.  

Drivers should use caution, follow signage and obey traffic rules. Check out these educational videos for a quick refresher on how to safely navigate roundabouts.

These videos were originally developed by the Region of Durham and depict a generic two-lane roundabout similar to the final Jeremy Ranch Roundabouts configuration.

Hotline: 833-9LETSGO (833-953-8746)

Email: info@letsgosummit.com
Website: www.letsgosummit.com