Hoytsville Road Project

HoytProj_small
COUNCIL SELECTED OPTION
At their regularly scheduled meeting on February 12, 2020, the Summit County Council selected road configuration Option 2, 2-11’ wide travel lanes and 2-6’ wide shoulders. This project widens the overall width of the road by about 4 ½ feet each side. The project will tie into driveway and parking areas in as smooth a manner as possible, widen/replace box culverts, and address known drainage issues. The project will not add the separated path, though adding this feature is possible at some point in the future should it be needed.

PROJECT BACKGROUND

Summit County is in the process of developing a project on Hoytsville Road for the summer of 2020 and future years. The project (spanning from SR-32 to Hobson Lane) will take several years to fund and complete. The project funded for 2020 amounts to about $1 million dollars. The number of years to complete the entire section of road within the County’s jurisdiction depends on the type and extent of project scope the County moves forward with. The more complex design and more expensive project might need to be phased over more years than a simpler and less costly project. In order to help us make that decision, we are soliciting opinions from the residents along the road.

The Eastern Summit County Transportation Master Plan shows Hoytsville Road having plenty of capacity to 2040, but recommends that when the road is improved, the road should be widened to include wider shoulders to accommodate non-motorized transportation such as pedestrians and bicycles. The County’s Regional Transportation Planning Director has recommended a separated path, 8 to 10 feet wide, be included in any project, though it is not required by AASHTO. Pedestrians now use the little bit of shoulder or walk on the gravel/dirt shoulders. Bicycles use the travel lane.

Below are three alternative projects, their estimated cost and the approximate number of years it would take to complete the project, assuming a consistent level of funding each year ($1 million). Note: It is possible that the County Council could allocate more dollars to this project in future years to finish faster, but we wanted to evaluate these options, and your opinions, relative to each other.

.

______________________________________________________________________________________
HoytOpt1_small

Option 1: Mill and Fill


Mill and Fill existing surface only (Grind off 3” and add 3” of new pavement), width remains the same at about 25 feet, two 11-foot-wide lanes and 1½ -foot wide shoulder on each side +/-)
  • Cost to complete all of Hoytsville Road is $2 million
  • Will take 2 years to complete.
HoytOpt2_small

Option 2: Widen Road to include two 6-foot shoulders and two 11-foot travel lanes (AASHTO minimum for traffic volumes)


Widen Road to include two 6-foot shoulders and two 11-foot travel lanes (AASHTO minimum for traffic volumes)
  • Cost to complete all of Hoytsville Road is $4.5 million
  • Will take 5 years to complete.
HoytOpt3_small

Option 3: Widen Road to include two 6-foot shoulders and two 11-foot travel lanes (AASHTO minimum for traffic volume) AND add 8-foot-wide separated path


Widen Road to include two 6-foot shoulders and two 11-foot travel lanes (AASHTO minimum for traffic volume) AND add 8-foot-wide separated path
  • Cost to complete all of Hoytsville Road is $6.5 million
  • Will take 7 years to complete.

Project Open House
January 28, 2020, 6-8 p.m.

Summit County Courthouse, Conference Room 1
(First Floor, inside the southern public entrance)

______________________________________________________________________________________

If you have any questions, contact Derrick Radke, PE – Public Works Director at 435-336-3978 or dradke@summitcounty.org, or Michael Kendell, PE – County Engineer at 435-336-3120 or mkendell@summitcounty.org.